cpm-engine
The forensically-defensible CPM engine. AACE-canonical. Daubert-disclosed. Bit-identical between JavaScript and Python.
Maintained by Critical Path Partners — a forensic-scheduling consultancy.
Quick start
npm install @critical-path-partners/cpm-engine
const E = require('@critical-path-partners/cpm-engine');
const result = E.computeCPM(
[
{ code: 'A', duration_days: 5, early_start: '2026-01-05', clndr_id: 'MF' },
{ code: 'B', duration_days: 3, clndr_id: 'MF' },
{ code: 'C', duration_days: 4, clndr_id: 'MF' },
],
[
{ from_code: 'A', to_code: 'B', type: 'FS', lag_days: 0 },
{ from_code: 'B', to_code: 'C', type: 'FS', lag_days: 0 },
],
{
dataDate: '2026-01-05',
calMap: { MF: { work_days: [1, 2, 3, 4, 5], holidays: [] } },
}
);
console.log('Project finish:', result.projectFinish); // 2026-01-21
console.log('Critical path:', result.criticalCodesArray); // ['A', 'B', 'C']
console.log('Engine version:', result.manifest.engine_version); // 2.8.0
That's it. Forward pass, backward pass, total float, free float, calendar arithmetic, P6-conventional date math, multi-jurisdiction holidays — all done.
Why this engine?
| Capability | cpm-engine | SmartPM | Acumen Fuse | Phoenix |
|---|---|---|---|---|
| Open source | yes | no | no | no |
| AACE-canonical method labels (29R-03 / 49R-06 / 52R-06) | yes | partial | partial | partial |
| FRE 707 / Daubert disclosure (built-in) | yes | no | no | no |
| JS-Python bit-identical parity | yes | n/a | n/a | n/a |
| Topology fingerprint hash (SHA-256, copy-detection) | yes | no | no | no |
| Kinematic delay dynamics (velocity / accel / jerk) | yes | no | no | no |
| Bayesian update with hierarchical pooling | yes | no | no | no |
| Multi-jurisdiction holiday calendars (66 jurisdictions) | yes | partial | partial | partial |
| MIT licensed | yes | no | no | no |
The engine math is a commodity. The competitive moat in forensic scheduling is the workflow, the discipline, and the Daubert posture — not the forward pass. Critical Path Partners open-sources the engine so any academic, any solo forensic, any contractor's internal scheduler can build on a defensible foundation.
What you can build
- Forensic delay analysis — windows analysis (AACE MIP 3.3), collapsed as-built (MIP 3.8), prospective TIA (MIP 3.6)
- Claim packages — owner-submission EOT bundles with cover letter, exhibits, mitigation logs
- Daubert disclosures — FRCP 26(a)(2)(B) reports, FRE 702/707 four-prong methodology statements
- Schedule risk analysis — Monte Carlo P10/P50/P80/P90, sensitivity tornadoes, Bayesian updates
- Schedule health — DCMA-14 assessment, A-F auto-grade, baseline-vs-current diff
- Multi-jurisdiction calendars — 66 jurisdictions (CA-FED + 13 provinces, US-FED + 50 states + DC)
AACE alignment
The engine implements the math behind these AACE Recommended Practices:
| RP | Title | Method labels emitted |
|---|---|---|
| 29R-03 | Forensic Schedule Analysis | MIP 3.3 / 3.5 / 3.6 / 3.8 |
| 49R-06 | Identifying the Critical Path | LPM, TFM, MFP |
| 52R-06 | Prospective Time Impact Analysis | MIP 3.6 prospective |
| 122R-22 | Quantitative Risk Analysis Maturity Model (QRAMM) | (badge surface) |
| PPG #20 (2nd Ed 2024) | Forensic Schedule Analysis Practice Guide | (general acceptance) |
Method labels are emitted in result.manifest.methodology — exactly the strings AACE peer-reviewers and opposing experts expect.
Verifiable provenance
Every computation emits a manifest:
result.manifest = {
engine_version: '2.8.0',
method_id: 'computeCPM',
activity_count: 3,
relationship_count: 2,
data_date: '2026-01-05',
calendar_count: 1,
computed_at: '2026-05-10T14:32:01.847Z',
}
Plus, for forensic provenance, every input carries a SHA-256 topology hash:
const hash = E.computeTopologyHash(activities, relationships);
console.log(hash.topology_hash); // 64-char hex over canonical (code, duration, sorted preds)
// Two XERs with identical hashes ARE the same schedule, regardless of UID rotation.
This is the single most important forensic feature in the engine. Bid-collusion detection, retroactive-manipulation detection, and copy-detection across XERs all rely on it. It is also the foundation that lets opposing counsel verify a CPP analysis post-hoc.
JavaScript - Python parity
The engine has a Python sibling (_cpp_common/scripts/cpm.py) used by every CPP forensic skill. The two implementations are kept bit-identical via cross-validation:
npm run crossval
# 13 fixtures × 153 checks. 0 deviations as of v2.8.0.
Plus a 282-activity real-XER stress test reports 0 mismatches.
This means a forensic analysis run in JavaScript (browser, Node) produces the same numbers as one run in Python (claims-preparation skill, MCP server, batch pipeline). Every CPP deliverable carries the same manifest regardless of which surface produced it.
Production use
The engine runs live at mcp.criticalpathpartners.ca — try it in your browser. The same cpm-engine.js file is served over the wire and embedded inline in every report CPP produces.
The CPP forensic suite (forensic-delay-analysis, claims-preparation, claim-workbench, time-impact-analysis, schedule-risk-analysis, collapsed-as-built, counter-claim-analysis) all consume this engine — the JS port for browser/MCP, the Python sibling for batch pipelines.
Citation
If you use this engine in academic work or expert-witness reports, please cite:
Fitkowski, D. (2026). cpm-engine: A forensically-defensible critical-path-method engine with AACE-canonical method labels and Daubert disclosure. Critical Path Partners. Version 2.8.0. https://github.com/danafitkowski/cpp-cpm-engine
Algorithm citations are in docs/citations.md. All citations have been verified against primary sources.
License
MIT — see LICENSE.
You can use this engine in commercial forensic consulting, in academic research, in your own scheduling product, in court-filed expert reports. Just keep the copyright notice. No support is implied; no warranty is provided. You are responsible for the conclusions you draw with the engine. A Daubert disclosure is built in (DAUBERT.md) — you may use it as a starting point for your own FRCP 26(a)(2)(B) report.
Release notes
v2.9.1 (2026-05-10) — synchronized release marker. Engine code (cpm-engine.js) is byte-identical to v2.8.0; the SHA-256 topology hash algorithm and all CPM math are unchanged. The tag exists because the surrounding CPP skill suite absorbed an emergency truncation-purge hotfix — 80+ data-truncation sites removed across 13 renderers, enforcing the discipline described in feedback_no_truncation.md: analyst-facing data must never be silently cropped. A new regression test (tests/test_no_data_truncation.py) blocks future violations at CI.
v2.8.0 (2026-05-10) — initial public release. See CHANGELOG.md.
Contributing
See CONTRIBUTING.md. Forensic correctness is enforced — every commit must pass 528 unit tests and 153 cross-validation checks. New citations require WebSearch-verified URLs. No fabricated case names. No LLM-generated narratives in core engine paths.
Companion repositories
Two companion repositories are public and consume this engine:
- cpp-xer-parser — Canonical Primavera P6 XER parser and generator
- cpp-critical-path-validator — Critical path validation and logic health assessment
Additional CPP skills (forensic-delay-analysis, claims-preparation, claim-workbench, time-impact-analysis, collapsed-as-built, counter-claim-analysis, schedule-risk-analysis) are private; contact Critical Path Partners for access.
Strategic note
CPP is a forensic-scheduling consultancy. The engine is open-source not as a loss-leader but as a deliberate inversion of the competitive landscape: the math is a commodity, the workflow and discipline are not. Every academic, every solo forensic, every contractor's internal scheduler now has a reason to install CPP and a citation pathway. The closed-engine competitors — SmartPM, ALICE, Nodes&Links, Acumen — cannot match this move because their valuations require the engine stay proprietary.
If you ship something built on this engine, we'd love to hear about it: danafitkowski@gmail.com.
サーバー設定
{
"mcpServers": {
"criticalpathpartners": {
"url": "https://mcp.criticalpathpartners.ca/mcp",
"transport": "streamableHttp"
}
}
}